Brett Martin Ltd
  Search
Product Selector
 
  Home
  Roofing
  Semi-Finished
  Building
  Daylight Systems
  Roof Ventilation & Drainage
  Rainwater
  Soil & Waste
  Underground
  Pipes
  Access
  Gullys
  Bends
  Branches
  Ultra-Rib
 Technical
 General
Information
 Access to Drains
 Chemical
Resistance
 Maintenance
 Rodding Access
 Technical
Information
 Installation
 General Pipe
Installation
 Flow Properties
 Choice of
Gradients
 Pipe Sizing
 Ease of Compaction
 Pipe Laying
 Special Protection
 Material for
Bedding
 Open Channel
Manholes
 Perforated Pipe
 Preformed
Inspection
Chambers
  Watersupply

  Drainage Info
 Installation


SPECIAL PROTECTION

GROUND LOADS
Where a rigid pipe of:-
a) less than 150mm diameter has less than 300mm depth of cover, or
b) 150mm or more diameter has less than 600mm depth of cover,

it should be surrounded with concrete either 100mm or the diameter of the pipe, whichever is greater, in thickness and have movement joints, at not more than 5m centres.

Where a flexible pipe has less than 300mm depth of cover under an area other than a vehicular area, it should have concrete paving slabs laid as bridging on granular or other flexible filling at least 75mm above the top of the pipe. Where a flexible pipe has less than 600mm depth of cover under a vehicular area it should have a reinforced concrete slab laid as bridging in a similar manner.

FIGURE 4
Protection For Flexible Pipes

Protection for flexible pipes


FIGURE 5
Bedding For Flexible Pipes


Bedding for flexible pipes
1. Provision shall be required to prevent ground water flow
in open trenches.
2. The barrel of the pipe shall have continuous bearing on
the floor of the trench or the granular fill.


The trench should not be opened too long in advance of pipe laying and should be backfilled as soon as possible. It is essential to ensure that the sides of the trenches are adequately supported in accordance with the requirements of BS6031.To minimise a possible hazard, a trench should be open for the minimum time practicable.

At the crown of the pipe and for 300mm, or one pipe diameter if greater, above it the width of the trench within any timbering should be as narrow as is practicable, but not less than the outside diameter of the pipe plus sufficient extra width (usually about 150mm) on each side of the pipe to provide access for making the joints and placing and compacting sidefill. Above this level, the trench may be of any convenient width.

If the "as-dug" material is suitable for use as bedding, the bottom of the trench may be trimmed to form the pipe bed. Otherwise, the trench should be excavated to an adequate depth below the invert level of the pipe to allow for the necessary thickness of bedding material. The thickness of bedding under the barrel of the pipes should be a minimum of 100mm, but in very wet or soft conditions or where the trench bottom is very irregular, it may be necessary to increase this thickness. Bedding should be properly compacted and finished so as to provide uniform support for the pipe. It is essential that bricks or other hard materials are not placed under the pipes for temporary or permanent support.

Material to be used for bedding and surrounding the pipes should be selected granular material, either available locally or, if necessary, brought to the site. Suitable materials are described in Table 1.

TABLE 1
SUITABLE MATERIAL FOR BEDDING AND
SURROUNDING PIPES

Nominal
pipe size (mm)
Material (complying with the
requirements of BS882:Part 2)
110 10mm, nominal single-sized aggregate
160 10mm or 14mm, nominal single-sized aggregate or 14 to 5 graded aggregate
220 and over 10mm, 14mm or 20mm, nominal single-sized aggregate, or 14 to 5 or 20 to 5 graded aggregate

Alternatively, granular material in accordance with the following materials for bedding recommendations and having a particular size not exceeding that in Table 1 depending on pipe size, may be used.

SPECIAL PROTECTION -SETTLEMENT

A drain which runs under a building should be surrounded by at least 100mm of granular or other flexible filling.
It is recommended that a drain, which passes through a wall or foundation, should either:-

a) pass through an opening giving at least 50mm clearance all round as shown in Fig 7(a); or
b) be built in with, on each side, flexible joints within 150mm and rocker pipes of maximum length 600mm as shown in Fig 7(b).
c) wall protection sleeves are available shown Fig 7(c).

FIGURE 7
PIPES PENETRATING WALLS

Pipes penetrating walls



Pipes penetrating walls

A drain which is at a level lower than the foundations of a building:-

i) where the trench is within 1m of the foundations, it should be filled with concrete up to the level of the underside of the foundations; or
ii) where the trench is more than 1m from the foundations, it should be filled with concrete to a level, below the level of the underside of the foundations, equal to the distance from the foundations less 150mm.

Flexible pipes must be wrapped in polythene before surrounding in concrete. The minimum thickness of the concrete surround should be 150mm or the diameter of the pipe, whichever is greater.

(Note: where a drain is to pass under a foundation it should be supported on piles, or where the ground is unstable, specialist advice should be sought on the required protective measures).

SPECIAL PROTECTION -
SURCHARGING


Where a drain is liable to surcharge, protective measures as described in standard BS8301: 1985 should be used.

MATERIALS FOR BEDDING

1 VISUAL EXAMINATION
Examine the material and reject any which contains pieces with sharp edges.

2 PARTICLE SIZE
The maximum particle size should generally not exceed 20mm. The presence of an occasional particle between 20mm and 40mm is acceptable provided the total quantity of such particles is only a very small fraction. If particles over 40mm are present, the material should be rejected.

The following test will ensure compliance with this recommendation.

A weighed representative sample of the material, about 50kg of the proposed material (about 2kg) should be sieved, using test sieves of 19mm and 38mm nominal mesh size (see BS410).

Note 1: To obtain a representative sample, about 50kg of the proposed material should be heaped on a clean surface and divided with a spade down the middle. One of these halves should then be similarly divided, and so on until the required sample is left.

Note 2: In the sieving, clumps of material that break up under light finger pressure may be helped through the sieve, but considerable force should not be used to squeeze oversize clumps through the mesh.

The material is not recommended if:
a) any particles are retained on the 38mm sieve,
or
b) more than 5% by mass of the sample is retained on the 19mm sieve.

 
  Previous Pages


   
 
Feedback © 2003 Brett martin All rights reserved